Port of RADES : Putting into operation dock No. 6

After approximately one year immobilization, the dock No. 6 ,dedicated to containers, has resumed services with the docking of the door-Passat container ship on 12 April 2017 , following the completion of reconstruction work of the wharf and medians adjacent and the fulfillment of the market reception and implementation formalities by the Merchant Marine and Ports authority in order to be available for the benefit of the Tunisian company of stevedoring and handling, Concessionaire of the port of Rades.

This wharf suffered considerable damage on 22 November 2016 as a result of the collision of the Ouedziz ship which has caused its immobilization and the engagement of a major reconstruction project since March 2016 for costs 2.6 million Dinars.